3

I am working right now with a C code for a client. I let her know that when I reach 50% of progress She will pay the first part. However I have now 80% solved because I want continue my work without report, I already took the first part of the payment.

I don't know. If I continue without informing my progress my clients will think that I am not doing anything, also months ago this situation happen to me I was informing daily my progress to my client and He said "You don't need to message every progress that you do" So I stop it doing that and then said "You are not informing you progress"

Someone who works with code or tech can write here: How it should be the best frequency to communicate progress to a client without bother her/him

2
  • 2
    Well, it depends on the scope of the project. Let's say a project is going to take 6 months, then updating the client after every week, or every two weeks would be a better practice. And if there's a project with a deadline of a week, it'll be better to update the client every one or two days.
    – MurtazaA
    Commented Sep 7, 2021 at 14:11
  • 1
    As a thought, when certain milestones in the project are complete there should be communication with the client.
    – agarza
    Commented Sep 7, 2021 at 17:44

1 Answer 1

4

This is something that the client has to answer, not us. It depends both on the client and the project.

For example, with one client, I was simply reporting each day what I did. That was voluntary but it helped the client know that I was doing something for the money I was charging.

With a different client, I'm working on a project on "spec" that they might need it. If I'm communicating once a month, that might be too much.

There is also a difference between 80% of the initial coding done and 80% of the project done. In my mind, to get a project to 80% done state, all the coding has to be done, the unit testing is finished, and the project is deep into integration testing. Too many developers give the impression to a client that once the coding is done, the project will be done. That is far from the truth. But that is why we see a lot of projects come here where the client claims that it is 80% done and can someone come in and finish it? They don't realize that they might be only 40% of the way through the project.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.