Skip to main content
Removed [client] tag (as per http://meta.freelancing.stackexchange.com/q/167/9), added [fixed-price]
Source Link

I am pretty good at estimating my time on a project. For this question lets, let's say it is for a simple WordPress website with a custom theme development. I have quoted and set my contract with my client to be $2500 for the project, as it will take a total of 45 hours of work.

Move on to theI've now spent 45 hours andon the project, but I am still not yet done. What is the process to go to the client and ask for more money because the build is taking longer than expected.? Is it even appropriate to ask the client for some more money to finish the project, or am I just stuck finishing the development and "working for free" at that point.? Should I begin putting a clause in my contract with a client to cover myself in this case?

I am pretty good at estimating my time on a project. For this question lets say it is for a simple WordPress website with a custom theme development. I have quoted and set my contract with my client to be $2500 for the project as it will take a total of 45 hours of work.

Move on to the 45 hours and I am still not done. What is the process to go to the client and ask for more money because the build is taking longer than expected. Is it even appropriate to ask the client for some more money to finish the project or am I just stuck finishing the development and "working for free" at that point. Should I begin putting a clause in my contract with a client to cover myself in this case?

I am pretty good at estimating my time on a project. For this question, let's say it is for a simple WordPress website with a custom theme development. I have quoted and set my contract with my client to be $2500 for the project, as it will take a total of 45 hours of work.

I've now spent 45 hours on the project, but I am not yet done. What is the process to go to the client and ask for more money because the build is taking longer than expected? Is it even appropriate to ask the client for some more money to finish the project, or am I just stuck finishing the development and "working for free" at that point? Should I begin putting a clause in my contract with a client to cover myself in this case?

Tweeted twitter.com/#!/StackFreelance/status/343699921846820864
Source Link
bretterer
  • 1.6k
  • 1
  • 14
  • 16

When is it ok to ask a client for more money?

I am pretty good at estimating my time on a project. For this question lets say it is for a simple WordPress website with a custom theme development. I have quoted and set my contract with my client to be $2500 for the project as it will take a total of 45 hours of work.

Move on to the 45 hours and I am still not done. What is the process to go to the client and ask for more money because the build is taking longer than expected. Is it even appropriate to ask the client for some more money to finish the project or am I just stuck finishing the development and "working for free" at that point. Should I begin putting a clause in my contract with a client to cover myself in this case?